Difference between revisions of "JEF meeting, July 14, 2023"
From GlueXWiki
(Created page with "Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection inform...") |
|||
Line 5: | Line 5: | ||
=Agenda= | =Agenda= | ||
− | |||
*'''Preparation of parts for ECAL modules''' -- Sasha | *'''Preparation of parts for ECAL modules''' -- Sasha | ||
+ | ** Crystals: | ||
+ | **: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> | ||
+ | **: - Spare crystals | ||
+ | ** Received all long signal cables from the first order (1200). Received 450 short signal cables | ||
+ | ** Procurement parts for the LMS: | ||
+ | **: - Waiting for 7,600 ft of optical fibers (August/September) | ||
* '''Module fabrication''' -- Sasha | * '''Module fabrication''' -- Sasha | ||
+ | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | ||
+ | ** All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total) | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
+ | ** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done | ||
+ | ** Tested, labeled, and bundled 53 bundles (out of 100) of signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables] | ||
+ | ** Removing signal cables from the FCAL and rearranging signal cables in the hall [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] [https://halldweb.jlab.org/wiki/index.php/Rearranging_FCAL_cables] | ||
+ | **: - 400 signal cables removed, need to re-label and bundle | ||
+ | **: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL) | ||
+ | ** Cutting optical fibers (800 fibers have been cut), gluing plastic caps (380 recently glued)[https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg] | ||
+ | ** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ||
+ | ** Test fabricated modules using LMS | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
− | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication | + | ** All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris) |
+ | ** Preparing setups for testing modules and dividers | ||
+ | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] | ||
+ | ** Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
+ | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] --> | ||
*'''Light monitoring system''' -- Arshak | *'''Light monitoring system''' -- Arshak | ||
* '''Simulations/Analysis''' | * '''Simulations/Analysis''' |
Revision as of 08:51, 14 July 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Spare crystals
- Received all long signal cables from the first order (1200). Received 450 short signal cables
- Procurement parts for the LMS:
- - Waiting for 7,600 ft of optical fibers (August/September)
- Crystals:
- Module fabrication -- Sasha
- All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2] - done
- Tested, labeled, and bundled 53 bundles (out of 100) of signal cables connected from the flash ADC to the patch panel [3]
- Removing signal cables from the FCAL and rearranging signal cables in the hall [4] [5]
- - 400 signal cables removed, need to re-label and bundle
- - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
- Cutting optical fibers (800 fibers have been cut), gluing plastic caps (380 recently glued)[6]
- Report from students
- Test fabricated modules using LMS
- Testing of PMT dividers -- Sasha / Vlad
- All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris)
- Preparing setups for testing modules and dividers
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Detector installation page
- Updates from the meetings with Tim's group [7]
- Discussion of the FCAL2 installation procedures [8]
- Final mapping of low-voltage cables
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis