=Agenda=
 
=Agenda=
 
 
*'''Preparation of parts for ECAL modules''' -- Sasha  
 
*'''Preparation of parts for ECAL modules''' -- Sasha  
 +
** Crystals:
 +
**: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> 
 +
**: - Spare crystals
 +
** Received all long signal cables from the first order (1200). Received 450 short signal cables
 +
** Procurement parts for the LMS:
 +
**: - Waiting for 7,600 ft of optical fibers (August/September)
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 +
** All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
 
* '''Ongoing projects''' -- Sasha, all
 
* '''Ongoing projects''' -- Sasha, all
 +
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done 
 +
** Tested, labeled, and bundled 53 bundles (out of 100) of signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]
 +
** Removing signal cables from the FCAL and rearranging signal cables in the hall [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] [https://halldweb.jlab.org/wiki/index.php/Rearranging_FCAL_cables]
 +
**: - 400 signal cables removed, need to re-label and bundle
 +
**: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
 +
** Cutting optical fibers (800 fibers have been cut), gluing plastic caps (380 recently glued)[https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg]
 +
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 +
** Test fabricated modules using LMS
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Procedures]'''
+
** All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris)
 +
** Preparing setups for testing modules and dividers
 +
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob
 +
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 +
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 +
** Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings]
 +
** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables]
 +
** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students]
 +
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
*'''Light monitoring system''' -- Arshak
 
*'''Light monitoring system''' -- Arshak
 
* '''Simulations/Analysis'''
 
* '''Simulations/Analysis'''

Revision as of 08:51, 14 July 2023

Meeting time and location:


Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Spare crystals
    • Received all long signal cables from the first order (1200). Received 450 short signal cables
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers (August/September)
  • Module fabrication -- Sasha
    • All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [2] - done
    • Tested, labeled, and bundled 53 bundles (out of 100) of signal cables connected from the flash ADC to the patch panel [3]
    • Removing signal cables from the FCAL and rearranging signal cables in the hall [4] [5]
      - 400 signal cables removed, need to re-label and bundle
      - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
    • Cutting optical fibers (800 fibers have been cut), gluing plastic caps (380 recently glued)[6]
    • Report from students
    • Test fabricated modules using LMS
  • Testing of PMT dividers -- Sasha / Vlad
    • All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris)
    • Preparing setups for testing modules and dividers
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak
  • Simulations/Analysis