Line 21: Line 21:
 
**: - 400 signal cables removed, need to re-label and bundle
 
**: - 400 signal cables removed, need to re-label and bundle
 
**: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
 
**: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
** Cutting optical fibers (800 fibers have been cut), gluing plastic caps (380 recently glued)[https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg]
+
**: - install two flash ADCs
 +
** Cutting optical fibers [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg]
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
** Test fabricated modules using LMS
+
** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules]
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
** All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris)
+
** All electronics components received, expect to ship them to the company to fabricate dividers today (Chris)
** Preparing setups for testing modules and dividers
+
 
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob

Revision as of 08:54, 14 July 2023

Meeting time and location:


Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Spare crystals
    • Received all long signal cables from the first order (1200). Received 450 short signal cables
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers (August/September)
  • Module fabrication -- Sasha
    • All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [2] - done
    • Tested, labeled, and bundled 53 bundles (out of 100) of signal cables connected from the flash ADC to the patch panel [3]
    • Removing signal cables from the FCAL and rearranging signal cables in the hall [4] [5]
      - 400 signal cables removed, need to re-label and bundle
      - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
      - install two flash ADCs
    • Cutting optical fibers [6]
    • Report from students
    • Test fabricated modules using LMS [7]
  • Testing of PMT dividers -- Sasha / Vlad
    • All electronics components received, expect to ship them to the company to fabricate dividers today (Chris)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak
  • Simulations/Analysis