Difference between revisions of "JEF meeting, July 14, 2023"
From GlueXWiki
(→Agenda) |
|||
Line 21: | Line 21: | ||
**: - 400 signal cables removed, need to re-label and bundle | **: - 400 signal cables removed, need to re-label and bundle | ||
**: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL) | **: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL) | ||
− | ** Cutting optical fibers | + | **: - install two flash ADCs |
+ | ** Cutting optical fibers [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg] | ||
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ||
− | ** Test fabricated modules using LMS | + | ** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules] |
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
− | ** All | + | ** All electronics components received, expect to ship them to the company to fabricate dividers today (Chris) |
− | + | ||
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob |
Revision as of 08:54, 14 July 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Spare crystals
- Received all long signal cables from the first order (1200). Received 450 short signal cables
- Procurement parts for the LMS:
- - Waiting for 7,600 ft of optical fibers (August/September)
- Crystals:
- Module fabrication -- Sasha
- All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2] - done
- Tested, labeled, and bundled 53 bundles (out of 100) of signal cables connected from the flash ADC to the patch panel [3]
- Removing signal cables from the FCAL and rearranging signal cables in the hall [4] [5]
- - 400 signal cables removed, need to re-label and bundle
- - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
- - install two flash ADCs
- Cutting optical fibers [6]
- Report from students
- Test fabricated modules using LMS [7]
- Testing of PMT dividers -- Sasha / Vlad
- All electronics components received, expect to ship them to the company to fabricate dividers today (Chris)
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Detector installation page
- Updates from the meetings with Tim's group [8]
- Discussion of the FCAL2 installation procedures [9]
- Final mapping of low-voltage cables
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis