JEF meeting, July 14, 2023

From GlueXWiki
Revision as of 09:09, 14 July 2023 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location:


Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Spare crystals
    • Received all long signal cables from the first order (1200). Received 450 short signal cables
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers (August/September)
  • Module fabrication -- Sasha
    • All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [2] - done
    • Prepare to move modules into Hall D [3]
    • Tested, labeled, and bundled (53 bundlesout of 100) of signal cables connected from the flash ADC to the patch panel [4]
    • Removing signal cables from the FCAL and rearranging signal cables in the hall [5] Rearranging_FCAL_cables - done
      - 400 signal cables were removed,re-labeled and bundled
      - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
      - install two flash ADCs
    • Cutting optical fibers and gluing plastic caps [6]
    • Report from students
    • Test fabricated modules using LMS [7]
  • Testing of PMT dividers -- Sasha / Vlad
    • All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak
  • Simulations/Analysis