Difference between revisions of "JEF meeting, July 28, 2023"

From GlueXWiki
Jump to: navigation, search
 
(3 intermediate revisions by one other user not shown)
Line 2: Line 2:
 
*9:30 am EST (JLab time) remote only
 
*9:30 am EST (JLab time) remote only
 
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]
 
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]
 
=Agenda=
 
 
  
 
=Agenda=
 
=Agenda=
Line 10: Line 7:
 
** Crystals:  
 
** Crystals:  
 
**: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span>   
 
**: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span>   
**: - Jane with students performed inspection of 88 crystals, expect to receive 66
+
**: - 70 SICCAS crystals were shipped to us
** Received all long signal cables from the first order (1200). Received 450 short signal cables [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/short_signal.jpg]  
+
** Received 600 short signal cables [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/short_signal.jpg], ready to label
 
** Procurement parts for the LMS:
 
** Procurement parts for the LMS:
 
**: - Waiting for 7,600 ft of optical fibers (August/September)  
 
**: - Waiting for 7,600 ft of optical fibers (August/September)  
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
** All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
+
** All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
** Fixing about 20 modules with small imperfections (overlapping Tedla)
+
** Finished with fixin about 20 modules with small imperfections (overlapping Tedlar)
 
* '''Ongoing projects''' -- Sasha, all
 
* '''Ongoing projects''' -- Sasha, all
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done   
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done   
** Prepare to move modules into Hall D [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move.jpg] [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move2.jpg]
+
** Prepare to move modules into Hall D [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move.jpg] [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move2.jpg], wrap modules with sort towels.
** Prepare space for the ECAL in Hall D. Move and install shelves. 70 modules have already been moved into the hall [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move3.jpg].
+
** Prepare space for the ECAL modules (shelves, etc.) in Hall D. Moved 134 CRYTUR and 475 SICCAS crystals (609 in total to Hall D)  [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move3.jpg].
** Tested, labeled, and bundled (53 bundlesout of 100) [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/signal_bundles.jpg] of signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]. Receive cartridges for the printer, will resume labeling and cable bundling today.
+
** Tested, labeled, and bundled (86 bundles out of 100) [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/signal_bundles.jpg] signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]. Receive cartridges for the printer, will resume labeling and cable bundling today.
 
** Removing signal cables from the FCAL and rearranging signal cables in the hall [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] [https://halldweb.jlab.org/wiki/index.php/Rearranging_FCAL_cables Rearranging_FCAL_cables] - done
 
** Removing signal cables from the FCAL and rearranging signal cables in the hall [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] [https://halldweb.jlab.org/wiki/index.php/Rearranging_FCAL_cables Rearranging_FCAL_cables] - done
 
**: - 400 signal cables were removed,re-labeled and bundled
 
**: - 400 signal cables were removed,re-labeled and bundled
 
**: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
 
**: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
 
**: - install two flash ADCs
 
**: - install two flash ADCs
** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg]
+
** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg], waiting for 7600 ft of optical fibers
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules] 644 modules have been tested.
+
** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules], 928 modules have been tested (need to update the wiki page)
 +
** Work on refurbishing LG modules (wrapping, PMTs, etc.)
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
** All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
 
** All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
Line 43: Line 41:
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
*'''Light monitoring system''' -- Arshak
 
*'''Light monitoring system''' -- Arshak
 +
 +
=Minutes=
 +
Attendees: Olga, Zisis, Igal, Sasha, Phil, Bill, Liping, Arshak, Axel, S.T.
 +
* 70 SICCAS crystals will be shipped to JLab
 +
* Short signal cables for dark room continue to arrive -- have 800 ready for labeling
 +
* No news on outstanding LMS fibers (expect 7600 feet with the next month or two?)
 +
* All modules on site have been fabricated, some needed to be refurbished
 +
** 928 modules have been tested using dark box in EEL
 +
** Wrapping in soft plastic in preparation for moving to hall (609 have already been transferred)
 +
** Preparing to start stacking insert crystals -- alignment analysis underway, need to add some shims
 +
* Arshak received fiber stripper, started stripping ends of fibers for integrating sphere, polishing continues
 +
* 86/100 cable bundles ready to go

Latest revision as of 07:50, 31 July 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - 70 SICCAS crystals were shipped to us
    • Received 600 short signal cables [2], ready to label
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers (August/September)
  • Module fabrication -- Sasha
    • All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
    • Finished with fixin about 20 modules with small imperfections (overlapping Tedlar)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [3] - done
    • Prepare to move modules into Hall D [4] [5][6], wrap modules with sort towels.
    • Prepare space for the ECAL modules (shelves, etc.) in Hall D. Moved 134 CRYTUR and 475 SICCAS crystals (609 in total to Hall D) [7].
    • Tested, labeled, and bundled (86 bundles out of 100) [8] signal cables connected from the flash ADC to the patch panel [9]. Receive cartridges for the printer, will resume labeling and cable bundling today.
    • Removing signal cables from the FCAL and rearranging signal cables in the hall [10] Rearranging_FCAL_cables - done
      - 400 signal cables were removed,re-labeled and bundled
      - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
      - install two flash ADCs
    • Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
    • Report from students
    • Test fabricated modules using LMS [12], 928 modules have been tested (need to update the wiki page)
    • Work on refurbishing LG modules (wrapping, PMTs, etc.)
  • Testing of PMT dividers -- Sasha / Vlad
    • All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak

Minutes

Attendees: Olga, Zisis, Igal, Sasha, Phil, Bill, Liping, Arshak, Axel, S.T.

  • 70 SICCAS crystals will be shipped to JLab
  • Short signal cables for dark room continue to arrive -- have 800 ready for labeling
  • No news on outstanding LMS fibers (expect 7600 feet with the next month or two?)
  • All modules on site have been fabricated, some needed to be refurbished
    • 928 modules have been tested using dark box in EEL
    • Wrapping in soft plastic in preparation for moving to hall (609 have already been transferred)
    • Preparing to start stacking insert crystals -- alignment analysis underway, need to add some shims
  • Arshak received fiber stripper, started stripping ends of fibers for integrating sphere, polishing continues
  • 86/100 cable bundles ready to go