(Agenda)
(Agenda)
Line 29: Line 29:
 
** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg], waiting for 7600 ft of optical fibers
 
** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg], waiting for 7600 ft of optical fibers
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules], 928 modules have been tested.
+
** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules], 928 modules have been tested (need to update the wiki page)
 +
** Work on refurbishing LG modules (wrapping, PMTs, etc.)
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
** All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
 
** All electronics components received, will be shiped to the company to fabricate dividers today (Chris)

Revision as of 09:14, 28 July 2023

Meeting time and location:

Agenda

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - 70 SICCAS crystals were shipped to us
    • Received 600 short signal cables [2], ready to label
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers (August/September)
  • Module fabrication -- Sasha
    • All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
    • Finished with fixin about 20 modules with small imperfections (overlapping Tedlar)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [3] - done
    • Prepare to move modules into Hall D [4] [5][6], wrap modules with sort towels.
    • Prepare space for the ECAL modules (shelves, etc.) in Hall D. Moved 134 CRYTUR and 475 SICCAS crystals (609 in total to Hall D) [7].
    • Tested, labeled, and bundled (86 bundles out of 100) [8] signal cables connected from the flash ADC to the patch panel [9]. Receive cartridges for the printer, will resume labeling and cable bundling today.
    • Removing signal cables from the FCAL and rearranging signal cables in the hall [10] Rearranging_FCAL_cables - done
      - 400 signal cables were removed,re-labeled and bundled
      - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
      - install two flash ADCs
    • Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
    • Report from students
    • Test fabricated modules using LMS [12], 928 modules have been tested (need to update the wiki page)
    • Work on refurbishing LG modules (wrapping, PMTs, etc.)
  • Testing of PMT dividers -- Sasha / Vlad
    • All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak