=Minutes=
 +
Attendees: Igal, Bill, Laveen, Sasha, Liping, Olga, Hakob, Vlad, S.T.
 +
* Installation was on on hold last week for test run in Hall D
 +
** Moved cables back to EEL from hall for bundling, testing and labeling
 +
** Almost all cables now in house, still receiving LV cables (should be finished in about a month)
 +
** Resume LMS installation week of March 18 pending radiation levels near beam line in insert
 +
* PMT divider fabrication continues:  now 1400 in total
 +
** George J. from detector support group tested another 54, now up to 919 tested
 +
** Plan is to install in rows and test in situ after making temporarily dark
 +
* Sasha and Laveen working on translation table for ECAL
 +
** Also plan to work on implementation of geometry in XML
 +
* Need to work on new ePAS -- temporary one expired on Friday

Latest revision as of 08:35, 18 March 2024

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV short cables: received, checked, labeled (last week)
    • - HV long cable, 18 ready (out of 36)
    • - HV distribution boards: in preparation
    • - LV cables: 100 cables received, 500 cables in total
    • - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
  • Ongoing projects -- Sasha / Vlad / Hakob / Laveen
    • - Tested and labeled all HV cables ! and about 100 LV cables
    • - Bundling short cables (groups of 7, 7, and 6 cables)
      • finished: LV - 7 layers, HV - 17 layers, signal - 4 layers
  • Testing of PMT dividers -- Sasha / Vlad / George
    • - Testing procedure [3]
    • - About 1400 dividers have been fabricated (Chris, Armen, Mindy)
    • - Started removing power regulators on the newly fabricated dividers
    • - George has tested 54 dividers (919 have been tested in total) [4].
    • - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
  • Analysis/Simulation

Minutes

Attendees: Igal, Bill, Laveen, Sasha, Liping, Olga, Hakob, Vlad, S.T.

  • Installation was on on hold last week for test run in Hall D
    • Moved cables back to EEL from hall for bundling, testing and labeling
    • Almost all cables now in house, still receiving LV cables (should be finished in about a month)
    • Resume LMS installation week of March 18 pending radiation levels near beam line in insert
  • PMT divider fabrication continues: now 1400 in total
    • George J. from detector support group tested another 54, now up to 919 tested
    • Plan is to install in rows and test in situ after making temporarily dark
  • Sasha and Laveen working on translation table for ECAL
    • Also plan to work on implementation of geometry in XML
  • Need to work on new ePAS -- temporary one expired on Friday