Difference between revisions of "JEF meeting, November 11, 2022"

From GlueXWiki
Jump to: navigation, search
(Agenda)
 
(4 intermediate revisions by the same user not shown)
Line 8: Line 8:
 
*'''Preparation of parts for FCAL2 modules''' -- Sasha  
 
*'''Preparation of parts for FCAL2 modules''' -- Sasha  
 
** Received 25 CRYTUR crystals during this week [https://halldweb.jlab.org/wiki/index.php/CRYTUR]
 
** Received 25 CRYTUR crystals during this week [https://halldweb.jlab.org/wiki/index.php/CRYTUR]
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 742 ]  
+
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 762 ]  
*** Available for wrapping: 782 - 742 = 40 (5 crystals were wrapped during last week)
+
*** Available for wrapping: 782 - 762 = 20 (20 crystals were wrapped during last week)
 
*** Mindy (DSG group) continues wrapping crystals
 
*** Mindy (DSG group) continues wrapping crystals
 
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts]
 
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts]
 
* '''Module fabrication'''  -- Sasha
 
* '''Module fabrication'''  -- Sasha
 
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ]
 
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ]
** Fabricated modules: <span style="color:#FF0000"> Total 1318 </span> (5 modules fabricated since last week)  
+
** Fabricated modules: <span style="color:#FF0000"> Total 1335 </span> (17 modules fabricated since last week)  
 
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 SICCAS]  
 
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 SICCAS]  
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 742 CRYTUR], available: 40
+
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 759 CRYTUR], available: 20
 +
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)]
 
* '''Preparation for the FCAL2 installation (coordination with Tim's group)''' -- Sasha
 
* '''Preparation for the FCAL2 installation (coordination with Tim's group)''' -- Sasha
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting November 2022]
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting November 2022]

Latest revision as of 10:32, 11 November 2022

Meeting time and location:

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda