Difference between revisions of "JEF meeting, November 17, 2023"

From GlueXWiki
Jump to: navigation, search
Line 15: Line 15:
 
** - Testing and labeling cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ]
 
** - Testing and labeling cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ]
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ]
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ]
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals]
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals] - done
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg].
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] - done
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Modules for prototype (25 are ready)]. All parts are ready to assemble 30 CCAL-style modules.
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Modules for prototype (25 are ready)] - done
** - All optical fibers are ready for installation. 3-D printed a mounting plate to couple fibers with the integrating sphere  [https://halldweb.jlab.org/detectors/fcal2/lms/is_plate.jpg] (Boby); the plate was also machined; 3-D printing a fiber tray (will be attached to the plate)
+
** -   [https://halldweb.jlab.org/detectors/fcal2/lms/is_plate.jpg]
 
** - Installation of the trigger and readout electronics
 
** - Installation of the trigger and readout electronics
 
*** - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
 
*** - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.

Revision as of 10:05, 17 November 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: all cables are ready. Received all needed long cables. Need to test redo 4 bundles (48 cables have been tested)
    • - signal patch panels are ready [1]
    • - HV cables: have received 50 short cables, have been testes and labeled. 440 cables are ready for installation. 36 long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The design of the LV distribution board has been finalized (discussion with Fernando, the power regulators will not be added to the design)
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [8]
    • - Tested 314 dividers [9] (59 last week)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.