*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 759 CRYTUR], available: 20 | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 759 CRYTUR], available: 20 | ||
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)] | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)] | ||
− | * ''' | + | |
+ | * '''Installation of the FCAL2 detector''' -- Sasha / Arshak | ||
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting November 2022] | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting November 2022] | ||
*** Detector cabling and patch panels for the FCAL insert | *** Detector cabling and patch panels for the FCAL insert |
Revision as of 09:47, 18 November 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 25 CRYTUR crystals during this week [1]
- Wrapped CRYTUR crystals: 762
- Available for wrapping: 782 - 762 = 20 (20 crystals were wrapped during last week)
- Mindy (DSG group) continues wrapping crystals
- List of available parts
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1335 (17 modules fabricated since last week)
- Installation of the FCAL2 detector -- Sasha / Arshak
- Updates from the meetings with Tim's group November 2022
- Detector cabling and patch panels for the FCAL insert
- Manpower and division of tasks
- Projects for summer students
- Meeting with the detector support group
- Updates from the meetings with Tim's group November 2022
- Light Monitoring System -- Arshak