Line 30: Line 30:
 
** Plastic caps have been glued to all fibers
 
** Plastic caps have been glued to all fibers
 
* '''Returning low-quality crystals to SICCAS''' -- Sasha
 
* '''Returning low-quality crystals to SICCAS''' -- Sasha
** 11 crystals were wrapped and placed into the box; they ready for shipping to SICCAS  
+
** 11 crystals were wrapped and placed into the box; they ready for shipping to SICCAS [https://halldweb.jlab.org/detectors/fcal2/crystals/QA_check/third_batch/crystals_for_shipment.pptx]
 
   
 
   
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''
 
** [https://halldweb.jlab.org/wiki/images/6/6f/Gemtrd_Oct23.pdf First look at impact of GEMTRD] -- Simon
 
** [https://halldweb.jlab.org/wiki/images/6/6f/Gemtrd_Oct23.pdf First look at impact of GEMTRD] -- Simon

Revision as of 20:28, 14 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: 1360 short cables, all long cables are ready
    • - signal patch panels are ready [1]
    • - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    • - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad
    • - Test setup is ready. About 30 dividers are ready for testing
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • Plastic caps have been glued to all fibers
  • Returning low-quality crystals to SICCAS -- Sasha
    • 11 crystals were wrapped and placed into the box; they ready for shipping to SICCAS [9]