Difference between revisions of "JEF meeting, September 1, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
Line 17: Line 17:
 
* '''Ongoing projects''' -- Sasha, all
 
* '''Ongoing projects''' -- Sasha, all
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done   
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done   
** All crystals moved to Hall D[https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move.jpg] [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move2.jpg].
+
** All crystals moved to Hall D[https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move.jpg] [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move2.jpg] - done
 
** Tested, labeled, and bundled all 100 (+ 2 spares) [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/signal_bundles.jpg] signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables] - done
 
** Tested, labeled, and bundled all 100 (+ 2 spares) [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/signal_bundles.jpg] signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables] - done
 
** Test and label 1100 short signal cables - ongoing
 
** Test and label 1100 short signal cables - ongoing

Revision as of 08:47, 1 September 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received 70 crystals from SICCAS. Visual inspection: 4 dim crystals, 8 with many chips (consider to send them back to SICCAS) [1][2]
      - Plan to send back about 10 crystals
    • Received 1100 short signal cables [3]
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers. PR department prepared PO but forgot to send it out
  • Module fabrication -- Sasha
    • All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [4] - done
    • All crystals moved to Hall D[5] [6][7] - done
    • Tested, labeled, and bundled all 100 (+ 2 spares) [8] signal cables connected from the flash ADC to the patch panel [9] - done
    • Test and label 1100 short signal cables - ongoing
    • Tested fabricated modules using LMS [10] - done (need to update the wiki page)
    • Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
    • Work on refurbishing LG modules. About 80 modules have small imperfections and have to be fixed (rejected during installation)
      - Mindy is re-wrapping crystals (12 during last week). She also continues soldering wires to the PMT connectors
    • Report from students
  • Testing of PMT dividers -- Sasha / Vlad
    • Received 10 dividers (first article) ! , going to test them during this week (Chris)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak