Difference between revisions of "Jan 15, 2009 Calorimetry"
From GlueXWiki
(→Tentative Agenda) |
(→Documents to Review) |
||
Line 16: | Line 16: | ||
= Documents to Review= | = Documents to Review= | ||
+ | |||
+ | # [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1173 | GlueX-doc-1173 Fine mesh pmts] | ||
= Tentative Agenda = | = Tentative Agenda = |
Revision as of 11:45, 15 January 2009
Teleconference Time: 11:00 EST/10:00 CST
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 39527048# (remember the "#")
Contents
Items for followup from Dec 22 meeting
- Resolution studies (Blake)
- Develop criteria for evaluating resolution studies
- Study impact of inactive material at the end of Bcal on acceptance.
- Check what configuration (thresholds, step sizes, stack? parameters for secondaries, etc) is being used for the Hall D simulations (Regina)
- Report on the Bfield components in the region of the Bcal readout (JLab for next meeting).
- Options for vendors delivering specific lead sheet sizes (Tim)
Documents to Review
Tentative Agenda
- Announcements
- FCAL Update
- FCAL Calibration Claire's Slides (PDF)
- BCAL Update
- Bcal construction schedule
- First Article Fibers from Kuraray arrive first week in February (need fiber handling procedures)
- Preparations in Alberta (MOU, space, construction manager, QA plans, machining Pb)
- Magnetic Field Update (Elton)
- Updates on SiPM tests
- Bcal construction schedule
- GlueX collaboration meeting
- Any other business
Minutes
Attending: