Difference between revisions of "May 7, 2020 CPP Design Meeting"
From GlueXWiki
(Created page with "= Meeting Time and Place == Thursday May 7, 2020, 1:30pm Bluejeans https://bluejeans.com/710246635/3638?src=calendarLink * Present - Elton, Dave, Stephanie, Llya, Rory (remot...") |
(→Minutes and Action Items) |
||
(11 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
= Meeting Time and Place == | = Meeting Time and Place == | ||
Thursday May 7, 2020, 1:30pm | Thursday May 7, 2020, 1:30pm | ||
− | Bluejeans https://bluejeans.com/ | + | Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink |
* Present - Elton, Dave, Stephanie, Llya, Rory (remote) | * Present - Elton, Dave, Stephanie, Llya, Rory (remote) | ||
Line 8: | Line 8: | ||
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/April_23,_2020_CPP_Design_Meeting#Minutes_and_Action_Items | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/April_23,_2020_CPP_Design_Meeting#Minutes_and_Action_Items | ||
* Overall description https://halldweb.jlab.org/DocDB/0041/004180/006/CPP_update_oct19.pdf | * Overall description https://halldweb.jlab.org/DocDB/0041/004180/006/CPP_update_oct19.pdf | ||
− | * | + | * FY2020 Procurement possibilities [[Media:CPP_Procurement_schedule.docx]] |
+ | * Design/Fab/Install schedule [[Media:CPP_install_schedule.pdf]] | ||
* 3D model - show progress | * 3D model - show progress | ||
− | * Alignment tolerances | + | * Alignment tolerances require fine adjustment [[Media:CPP_stand_iso.pdf]] |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
* Things to work out | * Things to work out | ||
− | ** Alignment | + | ** 90° connector [[Media:Rory's_slides.pdf]] |
+ | ** Gas line routing | ||
+ | ** Procurement/installation schedule | ||
+ | ** Alignment hardware | ||
** Electronics shielding [[Media:Muon_Chamber_Shielding.pdf]] | ** Electronics shielding [[Media:Muon_Chamber_Shielding.pdf]] | ||
− | ** Grounding | + | ** Grounding cutouts in steel |
** Complete structural analysis | ** Complete structural analysis | ||
** Develop installation plan | ** Develop installation plan | ||
Line 26: | Line 24: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
− | *Reviewed minutes of last meeting | + | * Reviewed minutes of last meeting |
− | * | + | * Looked at possible installation schedules. The detector will be installed after spring 2021 run |
− | * | + | * Looked at gas line clearances - looks like bend radius is small enough so lines do not extend any further than the electronics panels on either side. |
− | + | * Need to design gas distribution manifold | |
− | + | * Clearances cut in steel on 3D model look good | |
− | + | * Need to review buckling loads on box tube (Tim) | |
− | + | * Need to look at I-Beam reinforcement (Tim) | |
− | + | ||
− | + | ||
− | * | + | |
− | * | + | |
− | + | ||
− | + | ||
− | * Need to | + | |
− | * | + | |
* Set up new meeting in 2 weeks | * Set up new meeting in 2 weeks |
Latest revision as of 09:20, 21 May 2020
Meeting Time and Place =
Thursday May 7, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink
- Present - Elton, Dave, Stephanie, Llya, Rory (remote)
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/April_23,_2020_CPP_Design_Meeting#Minutes_and_Action_Items
- Overall description https://halldweb.jlab.org/DocDB/0041/004180/006/CPP_update_oct19.pdf
- FY2020 Procurement possibilities Media:CPP_Procurement_schedule.docx
- Design/Fab/Install schedule Media:CPP_install_schedule.pdf
- 3D model - show progress
- Alignment tolerances require fine adjustment Media:CPP_stand_iso.pdf
- Things to work out
- 90° connector Media:Rory's_slides.pdf
- Gas line routing
- Procurement/installation schedule
- Alignment hardware
- Electronics shielding Media:Muon_Chamber_Shielding.pdf
- Grounding cutouts in steel
- Complete structural analysis
- Develop installation plan
- Develop Design/operational/Maintenance Requirements
Minutes and Action Items
- Reviewed minutes of last meeting
- Looked at possible installation schedules. The detector will be installed after spring 2021 run
- Looked at gas line clearances - looks like bend radius is small enough so lines do not extend any further than the electronics panels on either side.
- Need to design gas distribution manifold
- Clearances cut in steel on 3D model look good
- Need to review buckling loads on box tube (Tim)
- Need to look at I-Beam reinforcement (Tim)
- Set up new meeting in 2 weeks