(Monday, March 9)
 
(12 intermediate revisions by one other user not shown)
Line 1: Line 1:
 
<- Back to [[Run Coordination Meetings:Fall2019 Run]]
 
<- Back to [[Run Coordination Meetings:Fall2019 Run]]
 
[https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2019-11/index.html Integrated trigger count]
 
[https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2019-11/index.html Integrated trigger count]
 +
 +
== Wednesday, March 11 ==
 +
# Last 24 hours
 +
#* Vacuum valve closed: opportunistic access for CCAL and FCAL until ~3 pm
 +
#* CCAL bases replaced and closed up for TAC run with low current while Hall C is offline (3/13-3/20)
 +
# Reports/Issues
 +
#* [https://logbooks.jlab.org/entry/3801391 BCAL VME crate rebooted] yesterday afternoon but random and PS pulser [https://logbooks.jlab.org/entry/3801924 restarted this morning]
 +
#* Slow [https://logbooks.jlab.org/entry/3801555 beam drifts] [https://logbooks.jlab.org/entry/3801565]
 +
#* [https://logbooks.jlab.org/entry/3801629 New FCAL channel failure near beam hole]
 +
#* [https://logbooks.jlab.org/entry/3801833 Top bubbler at the add line] (will be addressed today)
 +
#* [https://logbooks.jlab.org/entry/3801694#comment-28034 RCDB error] partially fixed for run 72158
 +
# Run Plan
 +
#* Production
 +
 +
== Tuesday, March 10 ==
 +
# Last 24 hours
 +
#* Pedestal run addressed BCAL hot channel, followed by production running
 +
#* Vacuum valve closed (investigation underway):  Opportunistic access now(?)
 +
# Reports/Issues
 +
#* [https://logbooks.jlab.org/entry/3801218 Rates and their ratios] (Alexandre)
 +
#* Energy jump (Alexandre)
 +
#* BCAL LED pulser is working [https://logbooks.jlab.org/entry/3800498] [https://logbooks.jlab.org/entry/3800712]
 +
#* Monitoring: [https://logbooks.jlab.org/entry/3800713 FDC occupancy]
 +
#* [https://halldweb.jlab.org/hdops/wiki/index.php/Shift_Guidelines_for_Shift_Leader Reminder for Shift Leaders] (Elton)
 +
# Run Plan
 +
#* Opportunistic access for FCAL and CCAL
 +
#* Production after access
  
 
== Monday, March 9 ==
 
== Monday, March 9 ==

Latest revision as of 06:53, 12 March 2020

<- Back to Run Coordination Meetings:Fall2019 Run Integrated trigger count

Wednesday, March 11

  1. Last 24 hours
    • Vacuum valve closed: opportunistic access for CCAL and FCAL until ~3 pm
    • CCAL bases replaced and closed up for TAC run with low current while Hall C is offline (3/13-3/20)
  2. Reports/Issues
  3. Run Plan
    • Production

Tuesday, March 10

  1. Last 24 hours
    • Pedestal run addressed BCAL hot channel, followed by production running
    • Vacuum valve closed (investigation underway): Opportunistic access now(?)
  2. Reports/Issues
  3. Run Plan
    • Opportunistic access for FCAL and CCAL
    • Production after access

Monday, March 9

  1. Last 72 hours
    • Issues with delivering full current to A/C. Back up now, but no RF recovery planned/available to recover gradient(?)
    • Production running when beam available over the weekend
  2. Reports/Issues
  3. Run Plan
    • Production
  4. Longer term
    • Hall C down for configuration change 3/13-3/20. Good opportunity for low current TAC run.

Friday, March 6

  1. Last 24 hours
    • Limited beam yesterday morning, followed by Hall access for Solenoid VCL work (Scot/Mark)
    • Steady production evening and overnight
  2. Reports/Issues
  3. Run Plan (Friday + Weekend)
    • May be some additional (short) injector tuning (A2 interception) today to keep Hall A's charge asymmetry down.
    • Production
  4. Longer term
    • Hall C down for configuration change 3/13-3/20. Good opportunity for low current TAC run.

Thursday, March 5

  1. Last 24 hours
  2. Reports/Issues
  3. Run Plan
    • Opportunistic access for solenoid work in parallel with injector tuning (1:00 pm)
    • Production