=Monday, September 12=
+
=Wednesday, September 14=
=== Over the Weekend ===
+
=== Past 24 Hours ===
 +
*Empty target production @200nA
 +
**Time spent on LHe target so far: empty: 27%, full: 73%
 +
**[https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2022-08/ Total triggers collected]
 +
*Shift summaries:
 +
** [https://logbooks.jlab.org/entry/4041249 0400-1000 14/09]
 +
** [https://logbooks.jlab.org/entry/4041194 2200-0400 13/09-14/09]
 +
** [https://logbooks.jlab.org/entry/4041109 1600-2200 13/09]
 +
** [https://logbooks.jlab.org/entry/4040931 1000-1600 13/09]
 +
** [https://logbooks.jlab.org/entry/4040829 0400-1000 13/09]
 +
 
 +
=== Issues ===
 +
[https://logbooks.jlab.org/entry/4041264 Beam position shifts on 5C11 YPOS]
 +
 
 +
=== Plan ===
 +
*[https://logbooks.jlab.org/entry/4041273 Maintenance day today]
 +
**FCAL Base replacement (Malte)
 +
**Installation of setup in PS for GEM-TRD
 +
**Beam restoration expected around 8:00PM
 +
*Fill LHe target
 +
*Take production data at 200nA
 +
 
 +
=Tuesday, September 13=
 +
=== Past 24 Hours ===
 
*[https://logbooks.jlab.org/entry/4040742 TAC run]
 
*[https://logbooks.jlab.org/entry/4040742 TAC run]
 
*Empty target production @200nA
 
*Empty target production @200nA
 +
**[https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2022-08/ Total triggers collected]
 
*Shift summaries:
 
*Shift summaries:
 
** [https://logbooks.jlab.org/entry/4040829 0400-1000 13/09]
 
** [https://logbooks.jlab.org/entry/4040829 0400-1000 13/09]
Line 21: Line 45:
  
 
=== Issues ===
 
=== Issues ===
*Active collimator
+
*[https://logbooks.jlab.org/entry/4040773 spontaneous saturation of active collimator adcs during TAC run]
 +
*[https://logbooks.jlab.org/entry/4040565 More data on LCW Temperature variations]
  
 
=== Plan ===
 
=== Plan ===

Latest revision as of 08:19, 14 September 2022

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook

Back to Run Coordination Meetings:Fall2022

Wednesday, September 14

Past 24 Hours

Issues

Beam position shifts on 5C11 YPOS

Plan

  • Maintenance day today
    • FCAL Base replacement (Malte)
    • Installation of setup in PS for GEM-TRD
    • Beam restoration expected around 8:00PM
  • Fill LHe target
  • Take production data at 200nA

Tuesday, September 13

Past 24 Hours

Issues

Plan

  • Empty Target running
  • Maintenance day tomorrow
    • Beam off around 6:30AM, restored during swing shift (~8PM)

Monday, September 12

Over the Weekend

Issues

  • FCAL Bases:
    • Had to reset a few bases throughout the weekend using standard procedure. One base (35,5) was not responding to power-reset and Malte will investigate next access.
    • Another base not holding HV and needs to be replaced next access
  • CDC AI turned off per Naomi's request.

Plan

  • Empty Target, take TAC Run
  • Continue taking empty-target data until Maintenance day on Wednesday

Friday, September 9

Past 24 hours

Issues

Plan

  • Continue taking production data at 200nA.
    • Production runs at small intensity (50nA and 100nA) over the weekend?
  • PrimEx Run Plan

Thursday, September 8

Past 24 hours

Issues

Plan