Difference between revisions of "May 03, 2023, FCAL Insert Installation Meeting"
From GlueXWiki
(→Minutes) |
(→Minutes) |
||
(4 intermediate revisions by the same user not shown) | |||
Line 8: | Line 8: | ||
== Agenda == | == Agenda == | ||
− | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/ | + | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/April_26,_2023,_FCAL_Insert_Installation_Meeting |
* Status of dis-assembly | * Status of dis-assembly | ||
− | ** Updated Work plan for module removal | + | ** Updated Work plan for module removal - Malte |
* Crystal/glass boundary | * Crystal/glass boundary | ||
** [[Media:Thermacool.pdf]] | ** [[Media:Thermacool.pdf]] | ||
** Samples in hand (.062" and .035", no glue) | ** Samples in hand (.062" and .035", no glue) | ||
* Discuss glass and crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha/Malte etc... | * Discuss glass and crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha/Malte etc... | ||
− | |||
*LMS decision? | *LMS decision? | ||
== Minutes == | == Minutes == | ||
− | * | + | * Reviewed minutes from last week |
− | * | + | ** Malte made a shift plan and will distribute on Google docs |
− | * Malte | + | **There is a need for 50 micron aluminized mylar for big holes - Scot will order |
− | * There | + | ** Some of the modules show cuts in the mylar from SS straps - does not seem to be increasing as we get lower in the stack |
− | * | + | ** Eugene requesting a "forked" tool to help keep tape straight |
− | ** | + | ** No shims have been observed in upper half yet - we need to document shims in the lower half as we unstack |
− | ** | + | ** Planning stacking test in ESB once the G10 plates are modified - approx 2 weeks |
− | ** | + | ** Sasha working with Stephanie and Arshak to determine LMS fiber lengths |
− | ** | + | *** Sasha to sketch box to see where it will fit under platform |
− | ** | + | *** There is a question about temperature stabilization in the box - is it needed? |
− | * | + | * We appear to be about 2 weeks ahead of schedule with unstacking going quicker than expected |
− | * | + | * Sasha is in charge of stacking and will make a plan |
− | * Sasha would like | + | * Malte expressed that we have enough shelving and crates for all glass modules - |
− | + | ** may need to stack 3 rows on some shelves | |
+ | ** Keith and Scot to look at was to make lower shelves more accessible | ||
+ | * Sasha mentioned that at some point we would like to remove some of the 400 unused cables for re-use |
Latest revision as of 07:32, 9 May 2023
Meeting Time and Place
Wednesday May 03, 2023 9am At Jefferson Lab, Hall D Counting House and on Zoom https://jlab-org.zoomgov.com/j/1619449114?pwd=UFlVQ1dWTGZ0ZkVYSEx5QzE4YUI3dz09&from=addon meeting ID: 161 944 9114 Passcode: 562689
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/April_26,_2023,_FCAL_Insert_Installation_Meeting
- Status of dis-assembly
- Updated Work plan for module removal - Malte
- Crystal/glass boundary
- Media:Thermacool.pdf
- Samples in hand (.062" and .035", no glue)
- Discuss glass and crystal module install, shimming etc... [1] - Sasha/Malte etc...
- LMS decision?
Minutes
- Reviewed minutes from last week
- Malte made a shift plan and will distribute on Google docs
- There is a need for 50 micron aluminized mylar for big holes - Scot will order
- Some of the modules show cuts in the mylar from SS straps - does not seem to be increasing as we get lower in the stack
- Eugene requesting a "forked" tool to help keep tape straight
- No shims have been observed in upper half yet - we need to document shims in the lower half as we unstack
- Planning stacking test in ESB once the G10 plates are modified - approx 2 weeks
- Sasha working with Stephanie and Arshak to determine LMS fiber lengths
- Sasha to sketch box to see where it will fit under platform
- There is a question about temperature stabilization in the box - is it needed?
- We appear to be about 2 weeks ahead of schedule with unstacking going quicker than expected
- Sasha is in charge of stacking and will make a plan
- Malte expressed that we have enough shelving and crates for all glass modules -
- may need to stack 3 rows on some shelves
- Keith and Scot to look at was to make lower shelves more accessible
- Sasha mentioned that at some point we would like to remove some of the 400 unused cables for re-use