Difference between revisions of "JEF meeting, May 3, 2024"
From GlueXWiki
Line 17: | Line 17: | ||
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ||
** - Mindy has finished with preparing all sockets (~1650) ! | ** - Mindy has finished with preparing all sockets (~1650) ! | ||
− | ** - All dividers have been fabricated | + | ** - All dividers have been fabricated and tested by George [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers] |
− | + | *** decided to remove regulators on about 40 dividers | |
− | + | ** - Adding ECAL and updating FCAL translation table in the TT.DB (have to finish during this week) | |
− | ** - Adding ECAL | + | |
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
** <span style="color: red"> Installation of the LMS has been completed </span> [https://logbooks.jlab.org/entry/4282307] | ** <span style="color: red"> Installation of the LMS has been completed </span> [https://logbooks.jlab.org/entry/4282307] |
Revision as of 09:07, 3 May 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV short cables: received, checked, labeled (last week)
- - HV long cable, 18 ready (out of 36)
- - HV distribution boards: in preparation
- - LV cables: waiting for about 160 cables (will need to test, label, and bundle)
- - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
- - Chris S. is working on the prototype of the LED board. Currently 5 blue LEDs, consider to add red LEDs as well
- Ongoing projects
- - Bundling short cables (groups of 7, 7, and 6 cables): signal (done), HV (done), LV (36 layers done, waiting for cables) [3]
- - Update from Laveen
- Testing of PMT dividers -- Sasha / Vlad / George / Mindy
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation of the LMS has been completed [6]
- Installation and testing cables and dividers [7][8]
- All crates are connected to the network switch Ethernet switch [9]
- Preparing for testing installed dividers
- Detector installation page
- Preparation for beam tests with the PS
- measure shower beam profile
- shower reconstruction between PbWO4 and LG
- Other hardware projects
- --prototype of the ECAL veto counter
- --study shower profile using PS (also transition region between lead tungstate and LG modules (?) )
- FCAL2 poster for open house?
- JEF/ECAL/FCAL poster
- Analysis/Simulation
- eta to ggpi0's update -- ig