Difference between revisions of "November 16, 2022 FCAL Insert Installation Meeting"
From GlueXWiki
(→Agenda) |
|||
Line 7: | Line 7: | ||
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting | ||
* Go through updated Gant chart | * Go through updated Gant chart | ||
+ | ** [[Media:FCAL2_schedule_v2.pdf]] | ||
** What inspections/marking/labeling/testing needed prior to glass block removal? | ** What inspections/marking/labeling/testing needed prior to glass block removal? | ||
** Surveys before removal | ** Surveys before removal | ||
Line 14: | Line 15: | ||
* Monitoring system discussion | * Monitoring system discussion | ||
* Assembly in ESB | * Assembly in ESB | ||
− | * | + | * |
[[image:Both_step.jpeg|thumb]] | [[image:Both_step.jpeg|thumb]] | ||
[[image:JBweld_cooling_test.jpeg|thumb]] | [[image:JBweld_cooling_test.jpeg|thumb]] |
Revision as of 15:38, 15 November 2022
Meeting Time and Place
Wednesday November 16, 2022 10am At Jefferson Lab, Hall D Counting House and on Teams
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting
- Go through updated Gant chart
- Media:FCAL2_schedule_v2.pdf
- What inspections/marking/labeling/testing needed prior to glass block removal?
- Surveys before removal
- Discuss Lead Glass and crystal module removal/install [1] - Sasha
- Manpower and task division [2] - Sasha
- Cable update
- Monitoring system discussion
- Assembly in ESB