Difference between revisions of "JEF meeting, December 1, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
Line 6: Line 6:
 
=Agenda=
 
=Agenda=
 
*'''Preparation of parts for ECAL''' -- Sasha  
 
*'''Preparation of parts for ECAL''' -- Sasha  
** - signal cables: all cables are ready. Received all needed long cables. Need to test redo 4 bundles (48 cables have been tested)
+
** - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
 
** - signal patch panels are ready [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ]
 
** - signal patch panels are ready [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ]
** - HV cables: have received 50 short cables, have been testes and labeled. 440 cables are ready for installation. 36 long cables are in production
+
** - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production
 
** - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
 
** - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
 
** - LV cables: ordered, lead time unclear
 
** - LV cables: ordered, lead time unclear
** - LV distribution boards. The design of the LV distribution board has been finalized (discussion with Fernando, the power regulators will not be added to the design)
+
** - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week.
 
** - Optical fibers: received all
 
** - Optical fibers: received all
 
* '''Ongoing projects''' -- Sasha, all
 
* '''Ongoing projects''' -- Sasha, all

Revision as of 10:13, 1 December 2023

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
    • - signal patch panels are ready [1]
    • - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables (Recently labeled cables in boxes)[2]
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
    • - Preparation of the LMS [5]
      • - 3-D print and machine mounting plate (coupling to the integrating sphere]
      • - 3-D print support structure for gluing fibers to the mounting plate [Boby]
      • - Machined Al plate for fiber polishing
      • - Installing fibers; will start gluing soon [6][7]
      • - The LMS should be ready for the installation on the detector during next week.
    • - Install labels on the detector [8]
    • - Installation of the trigger and readout electronics
      • - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
      • - Installed flash ADC, SDs, TIs. Uploaded new firmware [9]
      • - All readout controllers have been installed [10]
      • - Radiation tests of the PMT active base [11]
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [12]
    • - Tested 314 dividers [13] (59 last week)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
  • Analysis/Simulation