Difference between revisions of "JEF meeting, December 1, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 22: Line 22:
 
*** - All fibers have been glued to the mounting plate, which will be attached to the integrating sphere. The plate was machined and polised [https://logbooks.jlab.org/entry/4228633]
 
*** - All fibers have been glued to the mounting plate, which will be attached to the integrating sphere. The plate was machined and polised [https://logbooks.jlab.org/entry/4228633]
 
*** - Need to install light tight covers on the plastic caps. The fibers will be ready for installation after that.
 
*** - Need to install light tight covers on the plastic caps. The fibers will be ready for installation after that.
** - Install labels on the detector [https://halldweb.jlab.org/detectors/fcal2/lms/detector_label.jpg]
 
** - Installation of the trigger and readout electronics
 
*** - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
 
*** - Installed flash ADC, SDs, TIs. Uploaded new firmware [https://logbooks.jlab.org/entry/4208145]
 
*** - All readout controllers have been installed [https://logbooks.jlab.org/entry/4217259]
 
 
*** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
*** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]

Revision as of 10:17, 1 December 2023

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
    • - signal patch panels are ready [1]
    • - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [7]
    • - Tested 314 dividers [8] (59 last week)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
  • Analysis/Simulation