Difference between revisions of "JEF meeting, December 1, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 29: Line 29:
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
** Detector survey
+
** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]

Revision as of 10:21, 1 December 2023

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
    • - signal patch panels are ready [1]
    • - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [7]
    • - Tested 420 dividers [8] (104 last week)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Analysis/Simulation