(Agenda)
(Agenda)
Line 32: Line 32:
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
** Installation of the LMS  
 
** Installation of the LMS  
*** Started yesterday (after long delay) https://logbooks.jlab.org/book/hdlog]
+
*** Started yesterday (after long delay) [https://logbooks.jlab.org/entry/4243052]
 
*** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
 
*** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
 
** Cable and divider installation
 
** Cable and divider installation

Revision as of 10:23, 26 January 2024

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received 1280 in total
    • - HV distribution boards: in preparation
    • - LV cables: Received 48 cables during this week
    • - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors
    • - Optical fibers and parts for the trigger/DAQ have been ordered
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables [2], 120 short HV cables testes and labeled during this week.
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
      • 26 modules for TAC [3] and 35 modules [4] for the beam tests are ready
    • - Preparation of the LMS
      • - Need to glue Al flange to the optical fiber
      • - Ready for installation [5]
    • - Radiation tests of the PMT active base [6]
      • Finished tests, working on the tech note
    • - Inventory database and GUI for installed electronics
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [7]
    • - Tested 637 divider (all fabricated dividers) [8]
    • - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
    • Detector installation [9][10][11]
    • Installation of the LMS
      • Started yesterday (after long delay) [12]
      • Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
    • Cable and divider installation
      • Started yesterday, making a decision how to stretch them [13]
    • Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
    • Detector installation page