JEF meeting, March 8, 2024
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV short cables: received, checked, labeled (last week)
- - HV long cable, 18 ready (out of 36)
- - HV distribution boards: in preparation
- - LV cables: 150 cables received, 400 cables in total
- - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
- Ongoing projects -- Sasha, all
- - Tested and labeled all HV cables ! and about 100 LV cables -- Laveen
- Testing of PMT dividers -- Sasha / Vlad / George
- - Testing procedure [3]
- - About 1300 dividers have been fabricated (Chris, Armen, Mindy)
- - Started removing power regulators on the newly fabricated dividers
- - George has tested 133 + 41 = 174 dividers (811 tested in total) [4].
- - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
- Analysis/Simulation