Difference between revisions of "JEF meeting, November 10, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 16: Line 16:
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ]
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ]
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals]
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals]
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg]. All brass strap assemblies are ready.
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg].
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Modules for prototype (25 are ready)]. All parts are ready to assemble 30 CCAL-style modules.
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Modules for prototype (25 are ready)]. All parts are ready to assemble 30 CCAL-style modules.
 
** - All optical fibers are ready for installation. 3-D printed a mounting plate to couple with the integrating sphere  [https://halldweb.jlab.org/detectors/fcal2/lms/is_plate.jpg] (Boby); the plate was also machined; 3-D printing a fiber tray (will be attached to the plate)
 
** - All optical fibers are ready for installation. 3-D printed a mounting plate to couple with the integrating sphere  [https://halldweb.jlab.org/detectors/fcal2/lms/is_plate.jpg] (Boby); the plate was also machined; 3-D printing a fiber tray (will be attached to the plate)

Revision as of 10:13, 10 November 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: all cables are ready. Received 100 long cables. They have been tested, labeled and bundled (will be used to replace FCAL cables removed from the FCAL). Need to redo 10 bundls.
    • - signal patch panels are ready [1]
    • - HV cables: have received 50 short cables, have been testes and labeled. 440 cables are ready for installation. 36 long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The design of the LV distribution board has been finalized (discussion with Fernando, the power regulators will not be added to the design)
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables (Recently labeled cables in boxes)[2]
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
    • - All optical fibers are ready for installation. 3-D printed a mounting plate to couple with the integrating sphere [5] (Boby); the plate was also machined; 3-D printing a fiber tray (will be attached to the plate)
    • - Installation of the trigger and readout electronics
      • - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
      • - Installed flash ADC, SDs, TIs. Uploaded new firmware [6]
      • - All readout controllers have been installed [7]
      • - Irradiation tests of the PMT active base
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [8]
    • - Tested 255 dividers [9]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.


  • Analysis/Simulation