Line 15: Line 15:
 
** - Testing and labeling cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ]
 
** - Testing and labeling cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ]
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ]
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ]
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals]
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals] - done
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg].
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] - done
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Modules for prototype (25 are ready)]. All parts are ready to assemble 30 CCAL-style modules.
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Modules for prototype (25 are ready)] - done
** - All optical fibers are ready for installation. 3-D printed a mounting plate to couple fibers with the integrating sphere [https://halldweb.jlab.org/detectors/fcal2/lms/is_plate.jpg] (Boby); the plate was also machined; 3-D printing a fiber tray (will be attached to the plate)
+
** - Preparation of the LMS [https://halldweb.jlab.org/detectors/fcal2/lms/is_plate.jpg]
 +
*** - 3-D print and machine mounting plate (coupling to the integrating sphere]
 +
*** - 3-D print support structure for gluing fibers to the mounting plate [Boby]
 +
*** - Machined Al plate for fiber polishing
 +
*** - Installing fibers; will start gluing soon [https://halldweb.jlab.org/detectors/fcal2/lms/fibers_sphere1.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/fibers_sphere2.jpg]
 +
*** - The LMS should be ready for the installation on the detector during next week.
 +
** - Install labels on the detector [https://halldweb.jlab.org/detectors/fcal2/lms/detector_label.jpg]
 
** - Installation of the trigger and readout electronics
 
** - Installation of the trigger and readout electronics
 
*** - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
 
*** - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
 
*** - Installed flash ADC, SDs, TIs. Uploaded new firmware [https://logbooks.jlab.org/entry/4208145]
 
*** - Installed flash ADC, SDs, TIs. Uploaded new firmware [https://logbooks.jlab.org/entry/4208145]
 
*** - All readout controllers have been installed [https://logbooks.jlab.org/entry/4217259]
 
*** - All readout controllers have been installed [https://logbooks.jlab.org/entry/4217259]
*** - Irradiation tests of the PMT active base
+
*** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran / Boaxin
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran / Boaxin
 
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]
 
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]
** - Tested 255 dividers [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]
+
** - Tested 314 dividers [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers] (59 last week)
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
Line 37: Line 43:
 
** All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
 
** All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''
 +
** Added new JEF simulation page to [https://halldweb.jlab.org/wiki/index.php/JEF_Simulations wiki]
 +
** [https://halldweb.jlab.org/wiki/images/e/ef/Rate_studies.pdf Rate simulation studies]
 +
 +
=Minutes=
 +
Attendees: Sasha, Bill, Liping, Olga, Axel, Stjepa, Igal, Arshak, Phil, S.T.
 +
* All long signal cables are here, 3 new bundles ready to go
 +
* Short HV cables arriving slowly
 +
* LV cable status unclear -- potential bottleneck?
 +
* Production of LV distriubtino boards will happen soon
 +
* All parts are available for construcing 3x3/5x5 module arrays
 +
* 3D-printed parts for LMS are available, LMS ready for installation within a week
 +
**  Arshak recommends not using UV-curing glue
 +
* PMT divider tests continue, found 4-5 suspicious dividers
 +
* Testing radiation hardness of PMT base components with Cs source
 +
** 22.3 kRad total dose (to be compared to Sasha's estimate of 5 kRad/year at FCAL face)
 +
** Saw failure of DC regulator chip, as observed by NPS
 +
*** Regulator probably not needed, bypassed -> signal pulse restored
 +
* FCAL dark room being restored, canbus daisy chain almost done
 +
* Simon showed some preliminary rate estimates for FCAL-2 insert and potential inner-TOF veto at 900 nA

Latest revision as of 09:29, 20 November 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: all cables are ready. Received all needed long cables. Need to test redo 4 bundles (48 cables have been tested)
    • - signal patch panels are ready [1]
    • - HV cables: have received 50 short cables, have been testes and labeled. 440 cables are ready for installation. 36 long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The design of the LV distribution board has been finalized (discussion with Fernando, the power regulators will not be added to the design)
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables (Recently labeled cables in boxes)[2]
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
    • - Preparation of the LMS [5]
      • - 3-D print and machine mounting plate (coupling to the integrating sphere]
      • - 3-D print support structure for gluing fibers to the mounting plate [Boby]
      • - Machined Al plate for fiber polishing
      • - Installing fibers; will start gluing soon [6][7]
      • - The LMS should be ready for the installation on the detector during next week.
    • - Install labels on the detector [8]
    • - Installation of the trigger and readout electronics
      • - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
      • - Installed flash ADC, SDs, TIs. Uploaded new firmware [9]
      • - All readout controllers have been installed [10]
      • - Radiation tests of the PMT active base [11]
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [12]
    • - Tested 314 dividers [13] (59 last week)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
  • Analysis/Simulation

Minutes

Attendees: Sasha, Bill, Liping, Olga, Axel, Stjepa, Igal, Arshak, Phil, S.T.

  • All long signal cables are here, 3 new bundles ready to go
  • Short HV cables arriving slowly
  • LV cable status unclear -- potential bottleneck?
  • Production of LV distriubtino boards will happen soon
  • All parts are available for construcing 3x3/5x5 module arrays
  • 3D-printed parts for LMS are available, LMS ready for installation within a week
    • Arshak recommends not using UV-curing glue
  • PMT divider tests continue, found 4-5 suspicious dividers
  • Testing radiation hardness of PMT base components with Cs source
    • 22.3 kRad total dose (to be compared to Sasha's estimate of 5 kRad/year at FCAL face)
    • Saw failure of DC regulator chip, as observed by NPS
      • Regulator probably not needed, bypassed -> signal pulse restored
  • FCAL dark room being restored, canbus daisy chain almost done
  • Simon showed some preliminary rate estimates for FCAL-2 insert and potential inner-TOF veto at 900 nA