JEF meeting, November 3, 2023

From GlueXWiki
Revision as of 09:22, 3 November 2023 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: all cables are ready. Received 75 long cables. They have been tested, labeled and bundled (will be used to replace FCAL cables removed from the FCAL)
    • - signal patch panels are ready [1]
    • - HV cables: have received 100 short cables, have been testes and labeled. 320 cables are ready for installation. 36 long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards: met with Chris and Stephanie on Monday last week. The design of the LV distribution board has been finalized.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
Wrapped crystals
Parts for TAC[3]
Modules for prototype (25 are ready)
    • - Polished 320 fiber plastic caps, all fibers are ready. Meeting with Stephanie and Tim, 3-D printed a mounting plate to couple with the integrating sphere.
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [4]
    • - Tested 178 dividers [5]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • Plastic caps have been glued to all fibers
  • Returning low-quality crystals to SICCAS -- Sasha
    • 11 crystals were wrapped and placed into the box; they are ready for shipment to SICCAS [13]
  • Analysis/Simulation