JEF meeting, November 3, 2023

From GlueXWiki
Revision as of 10:05, 6 November 2023 by Staylor (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: all cables are ready. Received 75 long cables. They have been tested, labeled and bundled (will be used to replace FCAL cables removed from the FCAL)
    • - signal patch panels are ready [1]
    • - HV cables: have received 100 short cables, have been testes and labeled. 320 cables are ready for installation. 36 long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards: met with Chris and Stephanie on Monday last week. The design of the LV distribution board has been finalized.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables (Recently labeled cables in boxes)[2]
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
    • - Polished 320 fiber plastic caps, all fibers are ready. Meeting with Stephanie and Tim, 3-D printed a mounting plate to couple with the integrating sphere [5]
    • - Installation of the trigger and readout electronics
      • - 7 VXS crate, 3 HV crates, and 1 LV (Wiener) crate have been installed. Power lines will be installed in a week.
      • - Installed flash ADC, SDs, TIs. Uploaded new firmware [6]
      • - Work on the installation of ROCs and VTPs (with Ben R.)
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [7]
    • - Tested 178 dividers [8]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
    • Plastic caps have been glued to all fibers
  • Returning low-quality crystals to SICCAS -- Sasha
    • 11 crystals were wrapped and placed into the box; they are ready for shipment to SICCAS [16]
  • Analysis/Simulation

Minutes

Attendees: Sasha, Arshak, Phil, Liping, Igal, Jon, Olga, Jane, Vlad B., S.T.

  • 75 long signal cables arrived (out of 400)
    • Also using unused cables from FCAL, which are different in length by about 5 feet --> slightly different timing delays
  • LV patch panel design finalized
  • HV distribution being finalized
  • LV cables have not arrived
  • All optical parts for LMS are here
  • 100 short HV cables tested and labled (2 bad cables found)
  • Parts for making several small-scale lead tungstate detectors are ready
    • 3x3 array for use in PS test setup in hall
    • 5x5 array for measuring energy resolution, study shower profile -- using ECAL design
      • Fiber profiler?
    • 5x5 array to replace TAC using COMCAL design (no light guides)
  • 320 donuts for LMS polished
  • 3D printed disk with many holes for fibers for interface to integrating sphere has been constructed
  • Electronics for ECAL has been installed in hall
    • Found 2 bad flash ADC modules
    • Working on ROC/VTP installation
    • Aoran putting components into database
  • Checking of PMT dividers underway (recording waveform and peak amplitude)
    • 178 with PMT socket, found 3 bad dividers
    • Discussion with radcon regarding radiation damage
  • Canbus cables for lead glass being installed
  • Plexiglas for lead glass LMS not ready yet
  • 11 bad crystals sent back to SICCAS
  • Discussion regarding GlueX-III/JEF extension onging