(Created page with "== Meeting Time and Place == Wednesday May 03, 2023 9am At Jefferson Lab, Hall D Counting House and on Zoom https://jlab-org.zoomgov.com/j/1619449114?pwd=UFlVQ1dWTGZ0ZkVYSEx5...")
 
(Minutes)
 
(5 intermediate revisions by the same user not shown)
Line 8: Line 8:
  
 
== Agenda ==
 
== Agenda ==
* Minutes from last meeting  https://halldweb.jlab.org/wiki/index.php/March_26,_2023,_FCAL_Insert_Installation_Meeting
+
* Minutes from last meeting  https://halldweb.jlab.org/wiki/index.php/April_26,_2023,_FCAL_Insert_Installation_Meeting
 
* Status of dis-assembly
 
* Status of dis-assembly
** Updated Work plan for module removal
+
** Updated Work plan for module removal - Malte
 
* Crystal/glass boundary
 
* Crystal/glass boundary
 
** [[Media:Thermacool.pdf]]
 
** [[Media:Thermacool.pdf]]
 
** Samples in hand (.062" and .035", no glue)
 
** Samples in hand (.062" and .035", no glue)
 
* Discuss glass and crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha/Malte etc...
 
* Discuss glass and crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha/Malte etc...
* Cable update
 
 
*LMS decision?
 
*LMS decision?
  
 
== Minutes ==
 
== Minutes ==
* We went over minutes and action items from the previous meeting
+
* Reviewed minutes from last week
* Malte requested a log entry to be made everyday to keep track of how many modules were removed.
+
** Malte made a shift plan and will distribute on Google docs
* Malte to come up with a multi shift plan for unstacking and inspecting
+
**There is a need for 50 micron aluminized mylar for big holes - Scot will order
* There has been some difficulty un-torquing the bolts on the side pressure bars. Keith will break the torque on all the upper bars using the proper tools.
+
** Some of the modules show cuts in the mylar from SS straps - does not seem to be increasing as we get lower in the stack
* Sasha wishes to set up a stacking test
+
** Eugene requesting a "forked" tool to help keep tape straight
 +
** No shims have been observed in upper half yet - we need to document shims in the lower half as we unstack
 +
** Planning stacking test in ESB once the G10 plates are modified - approx 2 weeks
 +
** Sasha working with Stephanie and Arshak to determine LMS fiber lengths
 +
*** Sasha to sketch box to see where it will fit under platform
 +
*** There is a question about temperature stabilization in the box - is it needed?
 +
* We appear to be about 2 weeks ahead of schedule with unstacking going quicker than expected
 +
* Sasha is in charge of stacking and will make a plan
 +
* Malte expressed that we have enough shelving and crates for all glass modules -  
 +
** may need to stack 3 rows on some shelves
 +
** Keith and Scot to look at was to make lower shelves more accessible
 +
* Sasha mentioned that at some point we would like to remove some of the 400 unused cables for re-use

Latest revision as of 07:32, 9 May 2023

Meeting Time and Place

Wednesday May 03, 2023 9am At Jefferson Lab, Hall D Counting House and on Zoom https://jlab-org.zoomgov.com/j/1619449114?pwd=UFlVQ1dWTGZ0ZkVYSEx5QzE4YUI3dz09&from=addon meeting ID: 161 944 9114 Passcode: 562689

Agenda

Minutes

  • Reviewed minutes from last week
    • Malte made a shift plan and will distribute on Google docs
    • There is a need for 50 micron aluminized mylar for big holes - Scot will order
    • Some of the modules show cuts in the mylar from SS straps - does not seem to be increasing as we get lower in the stack
    • Eugene requesting a "forked" tool to help keep tape straight
    • No shims have been observed in upper half yet - we need to document shims in the lower half as we unstack
    • Planning stacking test in ESB once the G10 plates are modified - approx 2 weeks
    • Sasha working with Stephanie and Arshak to determine LMS fiber lengths
      • Sasha to sketch box to see where it will fit under platform
      • There is a question about temperature stabilization in the box - is it needed?
  • We appear to be about 2 weeks ahead of schedule with unstacking going quicker than expected
  • Sasha is in charge of stacking and will make a plan
  • Malte expressed that we have enough shelving and crates for all glass modules -
    • may need to stack 3 rows on some shelves
    • Keith and Scot to look at was to make lower shelves more accessible
  • Sasha mentioned that at some point we would like to remove some of the 400 unused cables for re-use