Difference between revisions of "Solenoid Coil Test in Test Lab"

From GlueXWiki
Jump to: navigation, search
m
m
Line 20: Line 20:
 
* Edit if needed, but be very careful.
 
* Edit if needed, but be very careful.
 
* Can print existing pdf file.
 
* Can print existing pdf file.
* [http://www.jlab.org/Hall-D/solenoid/Fastrack%20Schedules/Project.html Simple Web Version] of FastTrack schedule
+
* [http://www.jlab.org/Hall-D/solenoid/Fastrack%20Schedules/Project.html Simplified web version] of FastTrack schedule
  
  

Revision as of 13:03, 28 October 2009

Notes and To-Do lists for the 2009/2010 solenoid coil tests


Meetings


Project Milestones


FastTrack

  • George created initial FastTrack schedule in M:/halld/solenoid/FastTrack Schedules.
  • Edit if needed, but be very careful.
  • Can print existing pdf file.
  • Simplified web version of FastTrack schedule


System Diagrams and Related Documents

  • George put these in M:/halld/solenoid/Controls.


Electronic Log


Top To-Do Items

Note: Installation in Test Lab can begin once local coil repairs are complete, starting around 15-Nov-2009.


Oct-2009

  • Get overall system diagram, P&I, controls strategy to Mark Wissmann - George, Mark S
    • by 30-Oct-2009
  • Complete platform structural safety review - George, Suresh, contractor
    • by 30-Oct-2009
  • Complete overall assembly drawing - Wayne
    • by 30-Oct-2009

Nov-2009

  • Order cryo can - George
    • by 15-Nov-2009
  • Ship jack stands from IUCF - Tom
    • by 15-Nov-2009
  • Modify controls drawings for one chassis/coil and to include all planned instrumentation - Mark S, Slava
    • by 15-Nov-2009
  • Order remaining controls instrumentation - Mark S, Scott
    • by 15-Nov-2009
  • Finish ordering magnet spacer rings and related magnet components - George
    • by 15-Nov-2009
  • Complete design, order, fabrication and repair of magnet and yoke support components - George, Floyd, Kevin
    • by 15-Nov-2009
  • Finish design of cryo can power/control interface and pressure relief systems - Josh, James
    • by 15-Nov-2009
  • Statement of work, PO for IUCF coil repair work - George
    • by 30-Nov-2009
  • Complete coil 1 repair work - Kevin
    • by 30-Nov-2009
  • Order piping components - Tom
    • by 30-Nov-2009
  • Order platform and related components - Tom, George
    • by 30-Nov-2009
  • Arrange for coil storage space - Tom
    • by 30-Nov-2009
  • Get transportainer and rails from IUCF - George, Tom
    • by 30-Nov-2009
  • Start safety review process - George, Elliott
    • by 30-Nov-2009

Dec-2009

  • Arrange for space for coil 2 repair - Tom
    • by 15-Dec-2009
  • Install power supply in Test Lab- Tom
    • by 31-Dec-2009
  • Get 5 G field contours for different magnet currents - George, Floyd
    • by 31-Dec-2009

Feb-2010

  • Complete repairs at IUCF and ship coil to JLab - George, Tom
    • by 28-Feb-2009

Apr-2010

  • Complete coil 2 repairs - George
    • by 30-Apr-2010


Test Area

  • Notes:
    • Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
    • Bob Bennett is Test Lab "space czar."
    • Wayne is designing overall layout.
    • Will use SRF storage area for large power supply (6' x 5', 5' H, 5000 lbs) and switch (QWeak area unavailable).
    • Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
    • Platform is 172" x 160", cryo can will sit on top.
    • Platform must be removed to swap coils, and all connections to it must be broken.
    • Area has two 25T cranes, but need both (and strongback) to lift heaviest pieces (up to 45 tons).
    • Only a few dual-crane lifts needed.
    • Need come-alongs and anchors to move yokes and coils along rails.
    • Some areas will need to be roped off due to high B fields (5 G for pacemakers; other limits 60 G 8-hr body, 600 G 8-hr limb).
    • May need to remove some fences.
    • Magnet forces: 5 kG == 1 Atm, scales as square of B field.
    • When done, may leave infrastructure in place for magnet tests for other halls.
    • Coil center located 1/3 of the way along the long axis of our test area.
    • When saturated low field regions extend fairly uniformly around coil center in all directions. When not saturated low field regions extend out mainly along coil axis.


  • To Do:
    • Look into possibility of locating computer in control room (contact Joe Preble, Mark Drury)- Elliott
    • Investigate sensitivity of electronic equipment to B fields - Elliott
    • Determine areas to be roped off due to high B field - Floyd, George, Elliott
    • Prepare area for installation - Tom


  • Done
    • Enable building access for everyone - Elliott - done 19-Jun-2009 (same requirements as access to Cebaf Center)
    • Look into getting space in adjacent areas - George - done 2-Jul-2009
    • Distribute Floyd's B field map for single coil, no cladding, fine scale - George - done 9-Jul-2009
    • Determine location of all components - Wayne - done 29-Jul-2009
    • Determine how far cranes must be apart for dual-lift - George - done 29-Jul-2009
    • Order yoke strongback - George - done 27-Aug-2009


Infrastructure

  • Notes:
    • Platform borrowed from Hall A.
    • Must be moved to replace coils, 4-point lift.
    • Rails and transportainer currently at IU.
    • Have or can borrow all material moving equipment, or will contract out to rigging firm.
    • Have or can borrow all tools needed.
    • Controls racks coming from from computer center.
    • Need 60 W liquid He, Test Lab supply capable of 500 W, but share with Cryo group.
    • Must account for magnetic forces on all structures, perhaps as much as 20-30 Gauss static B field.
    • Electrical cables must be untouchable to 8 feet above floor.
    • Power supply is Danfysik MPS 854 system 8000 w/power input of 480VAC at 91Amps.
    • Power supplies requires 190 liters/min max at max 174psi, minimum differential pressure 43psi.
    • Found electrical switch so don't have to order one.
    • LN2 can relocated to platform so that we can use short U-tubes.
    • Test lab cryo can supply 3 g/s He.


  • To Do:
    • Produce overall system diagram - George
    • Produce construction/installation sequence - Wayne
    • Complete piping design - Tom
      • Design piping to vent N2.
      • Design warm and cold He supply/return systems, LN2 supply system.
      • Determine if any ODH considerations for N2 vent.
    • Retrieve rails/transportainer from IUCF - George, Tom
    • Install power supply cooling equipment, etc. - Tom
    • Arrange for electrical infrastructure installation - Tom, Mark S.


  • Done
    • Design structures and mechanical components, route cables, etc. - Wayne - done 29-Jul-2009
    • Get three racks from CC - Elliott, Tom - done 26-Oct-2009
    • Determine cryogen supply/return needs - George - done 26-Oct-2009
    • Arrange for cryogen supply/return with Dana Arenius (and Kelly Dixon?)- Tom - done 26-Oct-2009


Components

  • Platform
    • Entire platform and supports will be moved when changing coils.
    • Must account for magnetic forces.
    • Ladder needs to be shortened and straightened.
    • Must include cable trays and strain relief, especially for power connections.
  • Rails
    • Currently in transportainer at IU, George will have a look when he goes out there.
  • Cryo, U-tubes, can and heat exchanger
    • Bids in for cryo can, no contract or delivery date yet.
    • Heat exchanger from Hall A.
    • By moving LN2 can will not need to order U-tubes.
    • Will use Anaconda and borrowed short U-tubes.
  • Piping
    • Not clear where N2 vent will be routed.
    • Must incorporate drip pan under N2 vent due to icing.
    • May be ODH considerations.
  • Electrical power
    • Need to work out where outlets are needed.
  • Power supply
    • Resides in Physics Storage bldg.
    • Uses 3-phase 480 V.
    • 10V supply, 3000 A.
    • Integral dump resistor, may need rewiring to ensure always in coil circuit.
    • Need switch nearby.
    • Cables not water-cooled. 1.5" diameter cables, 1" copper.
  • Coils, rings and yokes
    • Buttresses are needed in coil 2.
    • Yoke modifications are needed.
    • Coil repairs will continue through summer 2009.
    • All must be leak-tested again.
    • Spacer rings designed in identical quadrants, two pieces per quadrant.
    • Need to design yoke jack stands.
  • Controls system
    • Is anything sensitive to B fields?
    • Will wire up as per final four-coil system.
    • Should use separate chassis for each coil, so we need to modify controls wiring diagrams.
    • Own DIN-mount RS232 module, can borrow power supply and ControlNet module from Steve L.
    • Steve L has cable and terminators, may need T-taps.
    • Not clear where computer will be located.
    • Should use high-quality color-coded terminal blocks.
    • Should use color-coded wiring, different color schemes for different systems.
    • We will instrument some thermocouples.
    • Must use appropriate wire (phosphor-bronze?) and wire insulation (Formvar?).
  • Misc tools, tables, chairs, ladders, etc.
    • What do we need? Can we beg, borrow, and/or steal?


  • To Do:
    • Design, order, install buttresses in coil 2 - George
    • Complete JLab coil repairs - George
    • Complete IUCF coil repairs - George
    • Understand how to deal with dump resistor in power supply - Mark S
    • Order cryo can - George
    • Get jack stands from IUCF - George, Tom
    • Get transportainer and rails from IUCF - George, Tom
    • Order magnet spacer rings - George
    • Design and order magnet/yoke support components - George, Floyd
    • Design and order piping - Tom
    • Design cryo and electrical break system for cryo can - Josh, James
    • Arrange for yoke modifications - George
    • Modify control wiring diagrams - Mark S, Slava
    • Order controls instrumentation - Mark S, Scott and Elliott
    • Get heat exchanger from Hall A - Mark S or Tom
    • Ensure we have all tools needed - Tom


  • Done
    • Verify we can borrow heat exchanger from Hall A - Mark S - done 2-Jul-2009
    • Determine if sensible to use one PLC chassis per coil - Mark S and Elliott - done 16-Jul-2009, yes!
    • Verify all cryo transfer lines and U-tubes are available on site - Mark S - done 29-Jul-2009
      • Situation changed 28-Aug-2009, may not be able to use Hall C U-tubes!
    • Complete coil 2 stress analysis - George, Floyd - done 20-Aug-2009
    • Borrow short U-tubes and Anaconda - Tom - done 26-Oct-2009


Programming

  • Notes:
    • Mark W will do all programming.
    • Can borrow lots of code from Steve Lassiter and co.
    • Single computer will perform all control and monitoring tasks.
    • Hall D P&I diagram will be the basis for control system design, James Lagner working on this.
    • P&I must include all vessels, valves, instrumentation, etc.
    • Need min/max flow rates, delta-T's, strain gauge readings, etc.
  • To Do:
    • Explain overall control strategy to Mark W - George, Mark S
    • Create complete P&I diagram for Mark W - George
    • Determine min/max flow rates, delta-T's, strain gauge values, etc. - George
    • Determine what needs to be archived and how often - George
    • Set up controls hardware in F117 - Mark S, Mark W and Elliott
    • Design and implement full control and archiving system - Mark W


  • Done
    • Install new memory in controls computer - Elliott and Mark W - done 6-Jul-2009
    • Borrow code from Steve Lassiter - Mark W - done 9-Jul-2009
    • Purchase new software licenses - Elliott - done 16-Jul-2009 none needed thanks to Steve Lassiter
    • Install all software on controls computer - Mark W - done 16-Jul-2009
    • Renew software update/maintenance contract - Elliott - done 27-Aug-2009
    • Update all software to latest version - Mark W - done 9-Sep-2009
    • Set up in test rack in ARC 101 - Mark W - done 15-Sep-2009


Staging

  • Notes:
    • Will instrument controls racks in F117, then move to Test Lab.
    • Will instrument for final 4-coil system.


  • To Do:
    • Rearrange F117 - Mark S
    • Verify adequate staging areas available in Test Lab - Tom


  • Done
    • Get and move 3 racks into F117 - Tom, Elliott - done 26-Oct-2009


Reviews

  • Notes:
    • Bob May and Paul Collins are contacts with EHS&Q for safety documentation and reviews
    • Need cryo, electrical, mechanical, and operations reviews.
    • Suresh Chandra responsible for structural review new platform and related components; will use outside consultant.
    • There will be a magnet review in Nov 2009.


  • To Do:
    • Write appropriate documentation - George, Mark S, Tom, Elliott
    • Set up all reviews - George and Elliott


  • Done
    • Mini-review of PLC vendor choice (Report from Omar Garza and Jonathan Creel) - done 15-Jun-2009
    • Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott - done 24-Jun-2009
    • Contact EH&S group concerning documentation and reviews - Elliott - done 29-Jun-2009


Construction

  • Notes:
    • Hall D is hiring a new Tech 1 and Tech 2 (Sep 2009).
    • What training do we all need?


  • To Do:
    • Get appropriate training - All
    • Order controls equipment - Mark S, Elliott and Scott
    • Arrange for telephone and networking in test area - Elliott
    • Arrange for installation of electrical infrastructure - Tom
    • Wire up controls racks - Mark S
    • Move controls racks to Test Lab - Mark S, Tom
    • Move computer to Test Lab - Mark W and Elliott
    • Install all components - Mark S, Tom
    • Hook up controls system - Mark S, Mark W and Elliott
    • Verify operation of control/archiving system - Mark W, Mark S, George and Elliott


  • Done


Coil Tests

  • Notes:
    • Purpose:
      • Verify correct operation of all coils.
      • Measure coil strains up to full current (1600 A).
    • Will take about six weeks per coil to install, cool down and test.
    • Only about 1 day of actual measurements per coil.
    • Nitrogen usage for the 300-80 K cooldown is ~18 to 21 g/s
    • 300-80 K cooldown: ~7 to 11 days
    • 80-4 K cooldown: ~2 to 4 days


  • To Do:
    • Create test plan - George


  • Done
    • Install electronic logbook system - Elliott - done 20-Aug-2009